[Insight-developers] Upcoming ITK release
Bill Lorensen
wlorens1 at nycap.rr.com
Mon, 12 Jan 2004 22:09:27 -0500
Looks like a plan.
Sounds good.
At 12:11 PM 1/12/2004, Brad King wrote:
>Hello,
>
>As discussed in Friday's TCON, we need a release for SPIE within a few
>weeks. Since we've had the major vnl upgrade, I think making this the 1.6
>release is justified. I need to fix several problems first (particularly
>with wrapping), and the dashboard needs to be cleaned up.
>
>I propose the following schedule to get this done ASAP:
>
>1.) Freeze features at the end of today (Monday, Jan 12, 2004).
>2.) Commit all fixes by Friday, freeze CVS at 5:00 EST Friday.
>3.) Bill L. and I will do final cleanups over the weekend.
>4.) Tag/branch ITK-1-6 on next Monday morning and re-open main CVS.
>
>Comments?
>-Brad
>
>_______________________________________________
>Insight-developers mailing list
>Insight-developers at itk.org
>http://www.itk.org/mailman/listinfo/insight-developers