[IGSTK-Developers] minutes from today and revised schedule

Kevin Cleary cleary at georgetown.edu
Thu Nov 3 18:24:37 EST 2005


Hi everyone:

 

Great tcon today as we had perfect attendance! (can't wait to see the CT of
Rick's throat though - I don't think I have ever seen a "throat CT" before)

 

I pasted the minutes on the Wiki although it wasn't much - just a recap of
some of the items we discussed

 

More importantly, I put the revised board review schedule on the Wiki and
pasted it below - note that I removed Brian Blake since he can't be there
(so now we have no discussion of requirements - maybe I should add this back
to the discussion somewhere), I added Rick Avila before lunch to discuss
project management and process, and I added Luis, Kevin, and David to the
state machine discussion

 

If you have any other comments on the schedule let us know

 

Meanwhile we managed to corrupt the firmware on the new Polaris Vicra -
supposedly we shouldn't be able to do this - it just goes to show you that
errors can happen! But we got new firmware for tech support at NDI and are
working away - I just wanted to let Luis and David know that Patrick will no
doubt be contacting you in the next few days as we try to get the example
application ready.

 

Thanks to all for their hard work on this project and I look forward to a
good meeting next week - but before we finish I want everyone to have a
clear direction of where the project is going and a plan for the next year

 

Kevin

  

------------------------------------------------------------------
Kevin Cleary, Ph.D.                        Work phone: 202-687-8253
Associate Professor                        Work fax: 202-784-3479
Deputy Director  
                            
Imaging Science and Information Systems (ISIS) Center
Department of Radiology                    Pager: 202-901-2033
Georgetown University Medical Center       Cell phone: 202-294-3409
2115 Wisconsin Avenue, Suite 603           Home phone: 301-299-0788
Washington, DC, 20007                      Home fax: 301-299-0789

 

ISIS center:  <http://www.isis.georgetown.edu/> www.isis.georgetown.edu
Research group:  <http://www.caimr.georgetown.edu/> www.caimr.georgetown.edu
WashCAS:  <http://www.washcas.org/> www.washcas.org
Email:  <mailto:cleary at georgetown.edu> cleary at georgetown.edu
-------------------------------------------------------------------

 

*  10 am: introduction to project and goals/objectives: Kevin Cleary 

*  10:30 am: demonstration of example applications 

*	Image-guided system for lung biopsy using optical tracking
(Polaris): Patrick Cheng 
*	Image-guided system for spine using electromagnetic tracking
(Aurora): James Zhang 

*  11 am: IGSTK architecture: Luis Ibanez 

*  11:30 am: IGSTK software development process: Kevin Gary 

*  11:50 am: IGSTK project management and process: Rick Avila 

*  12:10: lunch break to serve food (food to be brought in) 

*  1:00 pm: IGSTK state machine and state machine discussion 

*	First hour: twenty minute presentations by Luis, David, and Kevin 
*	Second hour: discussion 

*  3:00 pm: Error handling 

*  3:30 pm: IGSTK components 

*	Communications / tracking: David Gobbi 
*	Reader/writer: Andinet 
*	Visualization: Rick 
*	Spatial objects: Julien / Stephen 

*  4:30 pm: Wrap-up and summary

-------------- next part --------------
An HTML attachment was scrubbed...
URL: <http://public.kitware.com/pipermail/igstk-developers/attachments/20051103/72477f4f/attachment-0001.html>


More information about the IGSTK-Developers mailing list