[Cdash] Scheduling builds

David Cole david.cole at kitware.com
Thu Oct 6 17:45:18 EDT 2011


What did you put in the "repeat every ___ hours" field?

It looks like that is declared as a "numeric(3,2)" field, which means
3 total numeric digits, with 2 after the decimal point. So if you put
in larger than 9.99 or more than 3 digits altogether, it will not
work.

Why we chose numeric(3,2) for that field is beyond me, but that's
what's in the database schema. (Seems rather limiting, doesn't it?)

Use something between 0 and 9.99 for that value, and it should work ok.


HTH,
David


On Thu, Oct 6, 2011 at 12:40 AM, Tim Gallagher <tim.gallagher at gatech.edu> wrote:
> Hi,
>
> I'm trying to schedule a build but it doesn't seem to work. I get:
>
> [2011-10-06T00:28:16][ERROR][pid=16249](ClientJobSchedule::Save): SQL error: ERROR:  numeric field overflow
> DETAIL:  The absolute value is greater than or equal to 10^1 for field with precision 3, scale 2.
> [2011-10-06T00:28:16][ERROR][pid=16249](ClientJobSchedule::RemoveDependencies): SQL error: ERROR:  numeric field overflow
> DETAIL:  The absolute value is greater than or equal to 10^1 for field with precision 3, scale 2.
> [2011-10-06T00:32:15][ERROR][pid=16251](ClientJobSchedule::Save): SQL error: ERROR:  numeric field overflow
> DETAIL:  The absolute value is greater than or equal to 10^1 for field with precision 3, scale 2.
> [2011-10-06T00:32:15][ERROR][pid=16251](ClientJobSchedule::RemoveDependencies): SQL error: ERROR:  numeric field overflow
> DETAIL:  The absolute value is greater than or equal to 10^1 for field with precision 3, scale 2.
>
> in the log file. This is with the postgresql database. Does anybody have any insights?
>
> Thanks!
>
> Tim
> _______________________________________________
> Cdash mailing list
> Cdash at public.kitware.com
> http://public.kitware.com/cgi-bin/mailman/listinfo/cdash
>


More information about the Cdash mailing list